Data Centers Face Seven-Year Wait for Dominion Power Hookups
August 29, 2024
Dominion Energy Inc. expects the time it takes to connect large data centers to the electric grid to increase by one to three years amid a surge in requests, bringing the total wait time to as long as seven years.
The longer wait time applies only to large data centers that need more than 100 megawatts of electricity and won’t affect projects that have already been evaluated, according to a letter the company’s transmission arm sent its regulated utility as well as co-ops and local utilities. Almost all loads that big in Dominion’s territory are data centers.