Internet data centers are fueling drive to old power source: Coal
April 17, 2024
A helicopter hovers over the Gee family farm, the noisy rattle echoing inside their home in this rural part of West Virginia. It’s holding surveyors who are eyeing space for yet another power line next to the property — a line that will take electricity generated from coal plants in the state to address a drain on power driven by the world’s internet hub in Northern Virginia 35 miles away.
There, massive data centers with computers processing nearly 70 percent of global digital traffic are gobbling up electricity at a rate officials overseeing the power grid say is unsustainable unless two things happen: Several hundred miles of new transmission lines must be built, slicing through neighborhoods and farms in Virginia and three neighboring states. And antiquated coal-powered electricity plants that had been scheduled to go offline will need to keep running to fuel the increasing need for more power, undermining clean energy goals.